Chapter I General Provisions Article 1 The procedures and standards for the completion and acceptance of environmental protection facilities in construction projects are standardized,Strengthen the main responsibility of construction units for environmental protection,According to the Regulations on the Management of Environmental Protection of Construction Projects,These measures are formulated。 Article 2 These measures apply to the preparation of environmental impact reports (forms) and in accordance with the provisions of environmental protection laws and regulations, by the construction unit to implement the completion and acceptance of environmental protection facilities of construction projects and related supervision and management。 Article 3 The main basis for environmental protection acceptance of the completion of construction projects includes:: (1) Laws related to environmental protection of construction projects、statute、regulations、Standards and normative documents; (2) Technical specifications for environmental protection acceptance of construction projects; (3) The environmental impact report (form) of the construction project and the approval decision of the examination and approval department。 Article 4 The construction unit is the main body responsible for the environmental protection acceptance of the completion of the construction project,shall be in accordance with the procedures and standards set forth in these measures,Organize the acceptance of environmental protection facilities for supporting construction,Preparation of acceptance report,Disclose relevant information,Accept social supervision,Ensure that the environmental protection facilities that need to be built in the construction project are put into operation or used at the same time as the main project,and the acceptance of the content、Conclusions and veracity of the information disclosed、Accuracy and completeness are responsible,There shall be no fraud in the acceptance process。 Environmental protection facilities refer to the devices required to prevent and control environmental pollution and ecological damage and to carry out environmental monitoring、equipment and engineering facilities, etc。 The acceptance report is divided into an acceptance monitoring (investigation) report、Acceptance opinions and other matters that need to be explained。 Chapter II Procedures and Content of Acceptance Article 5 After the completion of the construction project,The construction unit shall be truthfully inspected、monitoring、Record the construction and commissioning of environmental protection facilities of construction projects,Preparation of acceptance monitoring (investigation) report。 Construction projects that mainly emit pollutants,Prepare the acceptance monitoring report with reference to the "Technical Guide for Environmental Protection Acceptance of Construction Project Completion" and Pollution Impact;Construction projects that have a major impact on the ecology,Prepare the acceptance investigation report in accordance with the "Technical Specifications for Environmental Protection Acceptance of Construction Projects Completion Ecological Impact Category".;Thermal power generation、Petroleum refining、Water conservancy and hydropower、Nuclear and radiation and other construction projects that have issued technical specifications for industry acceptance,Prepare acceptance monitoring reports or acceptance investigation reports in accordance with the acceptance technical specifications of the industry。 The construction unit does not have the ability to prepare the acceptance monitoring (investigation) report,It can be commissioned to a competent technical institution。The construction unit shall be responsible for the conclusion of the acceptance monitoring (investigation) report prepared by the entrusted technical institution。The relationship of rights and obligations between the construction unit and the entrusted technical institution,and the responsibilities of the entrusted technical institutions,It can be agreed in the form of a contract。 Article 6 It is necessary to debug the environmental protection facilities supporting the construction of the construction project,The construction unit shall ensure that the pollutant discharge during the commissioning period complies with the relevant national and local pollution discharge standards and relevant management regulations such as pollutant discharge permits。 Environmental protection facilities are not built at the same time as the main project,or should have obtained a pollutant discharge permit but did not do so,The construction unit shall not debug the environmental protection facilities of the construction project。 During commissioning,The construction unit shall monitor the operation of environmental protection facilities and the impact of construction projects on the environment。Acceptance monitoring shall ensure the stability of the commissioning conditions of the main project、It is carried out under the condition that the environmental protection facilities are in normal operation,And truthfully record the actual working conditions during monitoring。The relevant national and local pollutant discharge standards or industry acceptance technical specifications have other provisions on working conditions and production loads,It shall be implemented in accordance with its provisions。The construction unit carries out acceptance monitoring activities,According to their own conditions and abilities,Make use of your own personnel、Premises and equipment are monitored on their own;Monitoring could also be entrusted to other competent monitoring bodies。 Article 7 After the preparation of the acceptance monitoring (investigation) report is completed,The construction unit shall be based on the conclusion of the acceptance monitoring (investigation) report,Check one by one whether there is any unqualified acceptance listed in Article 8 of these measures,Put forward acceptance opinions。There is a problem,The construction unit shall carry out rectification,After the rectification is completed, the acceptance opinions can be put forward。 The acceptance opinions include the basic situation of the project construction、Changes in the project、Implementation of environmental protection facilities、Commissioning effect of environmental protection facilities、The impact of engineering construction on the environment、Acceptance conclusions and follow-up requirements,The acceptance conclusion shall clarify whether the environmental protection facilities of the construction project are qualified for acceptance。 After the experience of environmental protection facilities supporting the construction of the construction project is qualified,The main project can be put into production or use;It has not been accepted or the acceptance is unqualified,It shall not be put into production or use。 Article 8: Environmental protection facilities of construction projects have any of the following circumstances,The construction unit shall not put forward the opinion of passing the acceptance: (1) Failure to build environmental protection facilities in accordance with the requirements of the environmental impact report (form) and the approval decision of the examination and approval department,or the environmental protection facilities cannot be put into operation or used at the same time as the main project; (2) The discharge of pollutants does not comply with relevant national and local standards、The environmental impact report (form) and the approval decision of its examination and approval department or the total discharge control index of key pollutants are required; (3) After the environmental impact report (form) is approved,The nature of the construction project、scale、place、The production process used or the prevention and control of pollution、There has been a major change in measures to prevent ecological damage,The construction unit has not re-submitted the environmental impact report (form) for approval or the environmental impact report (form) has not been approved; (4) Major environmental pollution caused during the construction process has not been completed,or causing major ecological damage that has not been restored; (5) Construction projects included in the management of pollutant discharge permits,Discharging pollutants without a permit or discharging pollutants without a permit; (6) Phased construction、Construction projects that are put into production or used in phases and shall be accepted in phases in accordance with law,Its phased construction、The ability of environmental protection facilities put into production or use in phases to prevent and control environmental pollution and ecological damage cannot meet the needs of the corresponding main project; (7) The construction unit is punished for violating national and local environmental protection laws and regulations for the construction project,Ordered to make corrections,The correction has not been completed; (8) The basic data of the acceptance report are obviously untrue,There are significant deficiencies in the content、omit,Or the acceptance conclusion is not clear、irrational; (9) Other environmental protection laws, regulations, rules, and other provisions must not pass environmental protection acceptance。 Article 9 In order to improve the effectiveness of acceptance,In the process of putting forward acceptance opinions,The construction unit may organize the establishment of an acceptance working group,Take an on-site inspection、Access to information、Convening acceptance meetings, etc,Assist in carrying out acceptance work。Acceptance of the working group can be made up of design units、Construction unit、The organization that prepares the environmental impact report (form).、Acceptance, monitoring (investigation) report preparation agency and other unit representatives, as well as professional and technical experts,The scope and number of delegates are self-determined。 Article 10 The construction unit shall truthfully record the design of environmental protection facilities in the "other matters that need to be explained".、A brief overview of the construction and acceptance process、The implementation of environmental protection countermeasures other than environmental protection facilities proposed in the environmental impact report (form) and the approval decision of the examination and approval department,and the rectification work。 The relevant local government or government department promises to be responsible for the relocation of residents within the protective distance supporting the construction of the project、Functional replacement、Habitat protection and other environmental protection countermeasures,The construction unit shall actively cooperate with the local government or department to complete the project within the promised time limit,and truthfully record the implementation of the aforesaid environmental protection countermeasures in "other matters that need to be explained".。 Read More …